Premises Upgrade from 8 January 2007
On the 8th of January we commenced an upgrade project to replace the one-storey flat roof area
currently housing the Reception, waiting Area and Admin office with a two-storey
structure to link up with the existing building.
The upgrade will provide a two-storey structure with a new
pitched-roof to link up with the existing building. It will provide a new
Reception, Waiting Area, 5 consulting rooms, 3 examination rooms and a larger
pharmacy on the ground floor. The Admin Office, patient records room computer
server room will be relocated upstairs to release the much needed space on the
ground floor for patient care. The new larger Health Education Room will be used
for ante-natal classes, group smoking cessation classes, group psychotherapy
sessions and baby drop in clinics.
The upgrade project will last for 30 weeks. The building
work is expected to be completed by mid August 2007.
During this time there will be severe restriction on
parking as parking spaces will be very limited on site. We would be very
grateful if you could use alternative means of transport such as buses, taxis,
car share or lift with friends or relatives. Please allow extra time for
transport when you come to see the doctors and nurses.
We will use a portakabin as the main Reception and Waiting
Area. Lloyds Pharmacy will be operating in their specialised pharmacy portakabin
next to the Pharmacy. The Reception and Waiting Area for the Treatment Room will
be in the existing Health Education Room. A
walk-way will be built from the two portakabins to lead to the Doctors and
Treatment Room Areas.
We thank you for your understanding and co-operation.